Thursday, February 16, 2017

Project Update

Most of the exterior walls are set on 2nd floor at MWA - B


The stone veneer is nearly complete on the courtyard side of the building

We are pouring the last wall of building A today so the last couple
pre-cast planks can be set.

Elevator shaft on building A is up to the 2nd floor level.