Friday, March 24, 2017

Wednesday, March 1, 2017

Building C Update

Fourth floor insulation is complete.
We have also started hanging drywall on 4th.

Third floor insulation is moving along.



Thursday, February 16, 2017

Project Update

Most of the exterior walls are set on 2nd floor at MWA - B


The stone veneer is nearly complete on the courtyard side of the building

We are pouring the last wall of building A today so the last couple
pre-cast planks can be set.

Elevator shaft on building A is up to the 2nd floor level.

Friday, February 10, 2017

Update

Pre-cast is being grouted.
 





Club house barrel ceiling frames are being constructed.
 


Update

Pre-Cast is nearly complete for building A.
Today we will set most of the remaining plank and start grouting.




2nd floor trusses are set on building B
and we are starting sheathing.


Wednesday, February 1, 2017

Project Update

Getting ready to form the last of the footings on building A


Building B - 2nd floor trusses prepped and ready to set tomorrow.


Pre-cast columns are set on building A

Stone veneer is coming along nicely

Wednesday, January 18, 2017

Update

The 2nd pour of foundation A



Exterior wall on building B are getting built



Electrical service for building C is wrapped up and ready for permanent power.



Building C - 4th floor pre-insulation and pre-rock are starting