Monday, November 14, 2016

Project Update

The string line is up for the curbs and the curbs are being trimmed out.
The curbs will be poured later today.




 The underground plumbing is going in the parking garage of building B.


KS Energy is on site placing the conduit for the permanent power.


Huston is hauling off excess fill off site.


 Huston is also backfilling the foundation wall of building B.