Thursday, November 17, 2016

Update

Building A basement is dug, footing have been marked.



Digging the remainder of building A, near building C.

Building C 

 
Windows have arrived




Tuesday, November 15, 2016

Project Update

A large portion of building A has been excavated. We will finish Thursday and start digging footings.





4th floor deck is sheathed. Ready to start building walls.


Photo of the rebar cage being installed on the upper parking garage of building B.


Monday, November 14, 2016

Project Update

The string line is up for the curbs and the curbs are being trimmed out.
The curbs will be poured later today.




 The underground plumbing is going in the parking garage of building B.


KS Energy is on site placing the conduit for the permanent power.


Huston is hauling off excess fill off site.


 Huston is also backfilling the foundation wall of building B.


Friday, November 11, 2016

Project Update


4th floor trusses are set and sheathing is being installed.




The fire suppression system is being installed.



The masons are on site and starting the elevator shaft.



2/3 of the parking garage under building C is poured.
We will have the remainder finished by middle of week next week.



Building B - pre-cast is set and ready to start underground plumbing next week Monday. Also we are tying the steel cage for the foundation walls of the upper level parking garage.

Thursday, November 3, 2016

Building B - Pre-Cast

A busy day on site for pre-cast.
One crane is setting plank while the other crane is placing grout.



Tuesday, November 1, 2016

Project Update

Pre-cast is being set




Getting prepared to swing 4th floor trusses