4th floor trusses are set and sheathing is being installed.
The fire suppression system is being installed.
The masons are on site and starting the elevator shaft.
2/3 of the parking garage under building C is poured.
We will have the remainder finished by middle of week next week.
Building B - pre-cast is set and ready to start underground plumbing next week Monday. Also we are tying the steel cage for the foundation walls of the upper level parking garage.